Lenasia South’s Liverpool Block pipeline project resumes

The Liverpool Block pipeline project is expected to finish by the end of September. Residents have reported recent disruptions, while TILBIT Construction says it is working to minimise interruptions during drilling.

September 11, 2026

Construction work has resumed on the Liverpool Block pipeline project in Lenasia South Extension 1, with TILBIT Construction saying the project is now 60% complete and on track for the targeted 30 September completion date.

The R24-million Johannesburg Water project resumed in September after delays previously reported by GLOBE POST. The project forms part of a three-phase pipeline upgrade aimed at improving the area’s ageing water infrastructure and reducing recurring pipe bursts.

Tilbit said its teams are currently carrying out horizontal drilling at road crossings while continuing with pipe installation during Phase One along Newton Street.

The latest progress comes after the project faced several setbacks. In June, concerns were raised over unpaid wages involving general workers, while further delays were reported in August. Tilbit has since said all outstanding payments to general workers were settled on 30 July and that workers have been paid.

The contractor also previously told Globe Post that it had experienced no further challenges since returning to site. However, the continuation of construction has also brought new concerns about temporary disruptions in the affected area.

Residents in the Newton and Liverpool areas reported disruptions last Thursday, including an electricity interruption, while water later spread across part of the block. The incidents raised concerns about how construction activities are affecting existing services and access in the area.

Globe Post subsequently raised the concerns with the contractors. Tilbit said it is aware of the disruptions and explained that they occur when drilling is taking place as part of the construction work. The contractor also understands the impact the disruptions have on residents and will do its best to minimise them while the work continues.

The project also includes the installation of modern HDPE pipes, the replacement of ageing valves and fire hydrants, and the use of trenchless construction methods. Tilbit said it was not aware of any disconnected fire hydrants and that new above-ground hydrants would be installed in areas where it is working.

With construction now progressing towards the end-of-September target, residents can expect continued activity in the area as the contractor works on the remaining sections of the project.

Did this story inform, inspire or affect you?

Do not let important community news stop with you. Share this article with two friends, relatives or neighbours and help more people stay informed about what is happening in Lenasia, Ennerdale and Lawley South.

Follow Globe Post for trusted local reporting, community voices, breaking news and stories that matter.

Like it. Share it. Talk about it.

Join us on:

Together, we keep our community informed and connected.

Read more stories by

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Stories
  • Weekly Snapshot: Globe Post
    November 6, 2026
  • CSIR predicts DA at 33.3% in Johannesburg as ANC faces reduced support in 2026 elections
    November 5, 2026
  • Phumlamqashi residents face years of service delivery struggles as young voters demands change
    November 5, 2026
  • DA overtakes ANC to lead Johannesburg Ward 9 as Al Jama-ah closes in
    November 5, 2026

More stories like this

  • Entertainment, News, Sport
    From Eldorado Park to Bali: Young footballer’s dreams of taking kasi talent to the international stage
    November 4, 2026
  • News
    City Power technicians spotted on site as Grasmere residents await electricity restoration
    November 3, 2026
  • Environment, News
    A smoother road ahead: Finetown set for major infrastructure upgrade as 1.07km of gravel roads make way for asphalt
    November 3, 2026